Cliffemount is designing its energy bill before it opens

A family-owned hotel in Runswick Bay has reached roof level. Its Passivhaus ambition puts a useful hospitality question into the building itself.

Hotel energy costs are usually discussed when the bill arrives. At Cliffemount, a family-owned development overlooking Runswick Bay, they are helping shape the building before a guest checks in.

The 20-room hotel, pub and restaurant has reached its topping-out milestone, with the roof structure installed. Project manager Silverstone Building Consultancy says the opening is scheduled for autumn 2027. The owners are aiming for Passivhaus certification, rather than presenting this construction milestone as an award already achieved.

Karen Fojt and her family bought the former hotel in 2022. Their plan replaces the old building with a new development on the same coastal site. The hotel’s own account of the project makes sustainability part of the original brief, not an extra introduced once the design was settled.

That is what makes this a useful small-operator story. A hotel cannot decide whether it needs warm rooms only when energy prices rise. Comfort is part of the product. The interesting decision is how much energy the building needs to provide it, and how much capital an owner is prepared to commit before opening.

The technical ambition also has to work as hospitality. The AECB’s October site-tour description identifies traditional external materials alongside an airtightness strategy, substantial insulation and an air-source heat-pump system. Guest rooms, a restaurant and a pub have different patterns of use. A low-energy building still needs an operating team able to run those spaces effectively.

For another independent owner considering a refurbishment, there is no ready-made payback figure here. The information published does not provide a like-for-like capital-cost comparison or a measured annual saving. A new-build project is also a different proposition from improving an occupied hotel which must keep trading.

But it gives operators a better question to ask their project teams. Before choosing finishes or agreeing a budget, what will the building require to keep guests comfortable through the year? And who will check, after opening, whether actual performance matches the design?

The Passivhaus Trust’s earlier project account linked the choice of standard to rising fuel costs in hospitality. That is a commercial consideration as well as an environmental one. Reducing the energy a property needs could make its running costs less exposed to price changes, though construction, finance, staffing and demand still have to support the whole business.

Cliffemount has a considerable journey ahead before those results can be measured. For now, reaching roof level is tangible progress for a family taking a long-term approach to a small hotel. The next chapter worth following will be how the design performs when it becomes a working hospitality business.